Along with the same high electric power efficiency as before, will adopt a "liquid-cooling ready design" aimed at housing IT equipment for AI applications
May 8, 2025
Internet Initiative Japan Inc.
TOKYO - May 8, 2025 - Internet Initiative Japan Inc. (TSE Prime: 3774), one of Japan's leading Internet access and comprehensive network solutions providers, today announced plans for expansion of its Shiroi Data Center Campus ("Shiroi DCC"), a data center located in Shiroi City, Chiba Prefecture, with the construction of the phase 3 server building. Construction of the phase 3 building is scheduled to begin June 1, 2025, toward the planned start of operation during fiscal year 2026. With the phase 3 building, service facilities will be expanded further to meet growing demand for such IIJ service solutions as cloud, security, IoT, and MVNO, as client companies move ahead with digital transformation (DX) and make greater use of AI.
The phase 3 building will have a site area of approximately 5,400 square meters, maximum incoming power capacity of 10MW (expandable to 25MW), and scale of 1,000 racks. The building will adopt the same outside-air conditioning as the phase 1 and 2 buildings, realizing high electric power usage efficiency. In addition, a "liquid-cooling ready design" is being adopted, securing in advance the dedicated heat source space and cooling pipe routes needed for liquid cooling equipment, with a view to future accommodation of IT equipment having exceptionally high heat value such as GPU-equipped servers for AI use.
The Shiroi Data Center Campus began with the construction of the phase 1 server building in May 2019. Actively incorporating the latest energy-saving technology, AI, and automation technologies, it was built to meet large-scale data processing needs arising from progress in digital transformation (DX) and the spread of AI and IoT. In July 2023, operation of the phase 2 building began in response especially to strong demand for collocation service by cloud data center service providers, content providers and others. During 2026, the phase 2 building is expected to reach maximum capacity. Construction of the phase 3 server building announced here is mainly for the purpose of boosting facilities to accommodate IIJ's own service solutions as they continue to grow.
A "liquid-cooling ready design" is being adopted, securing in advance the space for installation of a dedicated heat source for liquid-cooling equipment such as DLC (Direct Liquid Cooling), and cooling pipe routes from the heat source to server rooms, anticipating the future use of IT equipment having exceptionally high heat value such as GPU-equipped servers for AI use. Flexible ceilings(*1) are also being adopted, enabling the rack position and ceiling opening locations in the server rooms to be changed readily as needed. This is to accommodate server racks with liquid-cooling equipment, which are larger than conventional racks and need more space for their power supply, as well as to meet needs for increased cooling capability. Moreover, the phase 3 building will have a hybrid structure, with the total area divided into zones and structural plans applied as suitable for each zone. The reason for this design is that the server rooms and electrical rooms in the building will have different structural load demands and different floor heights. In addition, technology gained from the joint research project on ultra-high-efficiency AI computing infrastructure(*2) will be utilized to the extent possible.
Aiming to be a carbon neutral data center, the Shiroi DCC adopts various air conditioning and cooling technologies and adopts other measures for raising the efficiency of electric power usage. The phase 3 building adopts an outdoor air cooling system making use of external air, and a wall-mounted blower scheme by which blowers mounted on walls that separate server rooms from the air conditioning machine room provide direct cooling of the server rooms. As electrical equipment, a three-phase, four-wire UPS(*3) enables efficient supply of electricity to 200V power supply equipment.
Phase 1 building | Phase 2 building | Phase 3 building | |
---|---|---|---|
Location | Shiroi City, Chiba Prefecture | ||
Overall site area | Approx. 40,000m2 | ||
Starting operation | May 2019 | July 2023 | Planned for FY2026 |
Maximum power received | 10MW | 10MW | 10MW (Expandable to 25MW in anticipation of liquid cooling and other increases in equipment density) |
Electrical equipment | Three-phase, four-wire UPS | ||
Air conditioning system | Direct outdoor-air cooling system | ||
Rack capacity | Approx. 700 racks | Approx. 1,100 racks | Approx. 1,000 racks |
IIJ will continue to offer stable infrastructure platforms by providing high-quality data center facilities and various added-value networking services.
About IIJ
Founded in 1992, IIJ is one of Japan's leading Internet-access and comprehensive network solutions providers. IIJ and its group companies provide total network solutions that mainly cater to high-end corporate customers. IIJ's services include high-quality Internet connectivity services, systems integration, cloud computing services, security services and mobile services. Moreover, IIJ has built one of the largest Internet backbone networks in Japan that is connected to the United States, the United Kingdom and Asia. IIJ was listed on the Prime Market of the Tokyo Stock Exchange in 2022.
The statements within this release contain forward-looking statements about our future plans that involve risk and uncertainty. These statements may differ materially from actual future events or results.